$0.00
CompTIA PK0-005 Exam Dumps

CompTIA PK0-005 Exam Dumps

CompTIA Project+ Certification (2024)

239 Questions & Answers with Explanation
Update Date : November 01, 2024
PDF + Test Engine
$65 $95
Test Engine
$55 $85
PDF Only
$45 $75

Money back Guarantee

We just do not compromise with the bright future of our respected customers. PassExam4Sure takes the future of clients quite seriously and we ensure that our PK0-005 exam dumps get you through the line. If you think that our exam question and answers did not help you much with the exam paper and you failed it somehow, we will happily return all of your invested money with a full 100% refund.

100% Real Questions

We verify and assure the authenticity of CompTIA PK0-005 exam dumps PDFs with 100% real and exam-oriented questions. Our exam questions and answers comprise 100% real exam questions from the latest and most recent exams in which you’re going to appear. So, our majestic library of exam dumps for CompTIA PK0-005 is surely going to push on forward on the path of success.

Security & Privacy

Free for download CompTIA PK0-005 demo papers are available for our customers to verify the authenticity of our legit helpful exam paper samples, and to authenticate what you will be getting from PassExam4Sure. We have tons of visitors daily who simply opt and try this process before making their purchase for CompTIA PK0-005 exam dumps.



Last Week PK0-005 Exam Results

147

Customers Passed CompTIA PK0-005 Exam

98%

Average Score In Real PK0-005 Exam

96%

Questions came from our PK0-005 dumps.



Authentic PK0-005 Exam Dumps


Prepare for CompTIA PK0-005 Exam like a Pro

PassExam4Sure is famous for its top-notch services for providing the most helpful, accurate, and up-to-date material for CompTIA PK0-005 exam in form of PDFs. Our PK0-005 dumps for this particular exam is timely tested for any reviews in the content and if it needs any format changes or addition of new questions as per new exams conducted in recent times. Our highly-qualified professionals assure the guarantee that you will be passing out your exam with at least 85% marks overall. PassExam4Sure CompTIA PK0-005 ProvenDumps is the best possible way to prepare and pass your certification exam.

Easy Access and Friendly UI

PassExam4Sure is your best buddy in providing you with the latest and most accurate material without any hidden charges or pointless scrolling. We value your time and we strive hard to provide you with the best possible formatting of the PDFs with accurate, to the point, and vital information about CompTIA PK0-005. PassExam4Sure is your 24/7 guide partner and our exam material is curated in a way that it will be easily readable on all smartphone devices, tabs, and laptop PCs.

PassExam4Sure - The Undisputed King for Preparing PK0-005 Exam

We have a sheer focus on providing you with the best course material for CompTIA PK0-005. So that you may prepare your exam like a pro, and get certified within no time. Our practice exam material will give you the necessary confidence you need to sit, relax, and do the exam in a real exam environment. If you truly crave success then simply sign up for PassExam4Sure CompTIA PK0-005 exam material. There are millions of people all over the globe who have completed their certification using PassExam4Sure exam dumps for CompTIA PK0-005.

100% Authentic CompTIA PK0-005 – Study Guide (Update 2024)

Our CompTIA PK0-005 exam questions and answers are reviewed by us on weekly basis. Our team of highly qualified CompTIA professionals, who once also cleared the exams using our certification content does all the analysis of our recent exam dumps. The team makes sure that you will be getting the latest and the greatest exam content to practice, and polish your skills the right way. All you got to do now is to practice, practice a lot by taking our demo questions exam, and making sure that you prepare well for the final examination. CompTIA PK0-005 test is going to test you, play with your mind and psychology, and so be prepared for what’s coming. PassExam4Sure is here to help you and guide you in all steps you will be going through in your preparation for glory. Our free downloadable demo content can be checked out if you feel like testing us before investing your hard-earned money. PassExam4Sure guaranteed your success in the CompTIA PK0-005 exam because we have the newest and most authentic exam material that cannot be found anywhere else on the internet.


CompTIA PK0-005 Sample Questions

Question # 1

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult? 

A. Gantt chart
B. Maintenance window schedule
C. Functional requirements
D. Test results



Question # 2

Which of the following describes three-tier architecture?

A. Conceptual, design, and implementation stages
B. Presentation, application, and data processing
C. Network, software, and security
D. Development, testing, and production environment



Question # 3

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

A. Make an impact assessment.
B. Prepare a new purchase order.
C. Select a new vendor.
D. Create a risk register.



Question # 4

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

A. RFI
B. RACI
C. WBS
D. SOW



Question # 5

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take? 

A. Exploit the risk.
B. Accept the risk.
C. Avoid the risk.
D. Transfer the risk.



Question # 6

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

A. Decline because it is not included in the project scope.
B. Assess the impact of the request and create a change request
C. Create new functional and non-functional requirements for mobile devices.
D. Revise the baseline of the project plan by adding the new requirements.



Question # 7

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

A. Kanban board
B. Pareto chart
C. Ishikawa diagram
D. Decision tree



Question # 8

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider? 

A. Resource allocation
B. Communication security
C. Technological factors
D. Cultural differences



Question # 9

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins? 

A. Time and materials contract
B. Master service agreement
C. Fixed-price contract
D. Statement of work
E. Statement of work



Question # 10

In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform? 

A. Assemble a new project with existing resources.
B. Obtain the final report from release management.
C. Notify the functional manager that resources are released.
D. Allocate resources in a different project



Question # 11

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

A. Escalate the finding to the change control board.
B. Add a risk to the risk register for validation.
C. Consult the RACI matrix to identify ownership of the risk.
D. Have a meeting with the project sponsor and main stakeholders.



Question # 12

Which of the following software programs would be BEST to use lo store information related to business transactions? 

A. Record management system
B. Customer relationship management
C. Enterprise resource planning
D. Content management system



Question # 13

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation? 

A. Responsibility assignment matrix
B. Acceptable communication channels
C. Risk registry
D. Staff directory



Question # 14

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

A. ROI.
B. SOW.
C. RFI.
D. RPR



Question # 15

A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team? 

A. Create a list of tasks and share it with the team.
B. Resend the scope of work to the team.
C. Review the Gantt chart weekly with the team.
D. Have the project sponsor meet with the team.



Question # 16

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

A. Work with the project scheduler to update the project timeline.
B. Communicate to the stakeholders about the updated timeline.
C. Ask the development team to fast-track upcoming activities.
D. Add two resources so the critical activities will finish on time.



Question # 17

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains: • Purpose • Scope of work • Location of work • Period of performance • Deliverables schedule • Applicable standards • Acceptance criteria • Special requirements • Payment schedule Which of the following documents did the client provide to the project manager?

A. RFP  
B. WBS   
C. SLA  
D. SOW  



Our Clients Say About CompTIA PK0-005 Exam